This is the screen that will appear when
you clicked the link "View" under the "Inspections"
column previously.
- You can view the status of any inspection
from here.
- Important: You will notice
a column marked GRP on this screen. This stands for Group,
and could also be referred to as "Sequence".
- This refers to the sequential order
that an inspection would occur in the construction process. Inspections
with a "0" can happen at any time in the construction
process. Inspections with a "1" have to occur before an
inspection marked "2". All inspections in Group 1 have
to be complete before any in Group 2 or higher can be scheduled.
- To schedule an inspection click
on the "Schedule" link under the Schedule column listed
on the row of the inspection you want to schedule.